Managing Change

News Image

Looking ahead and planning for change is essential in most aspects of life. Managing change effectively is an integral part of any project or programme delivery, and is therefore integral to dB’s business as the UK’s largest broadcast systems integrator.

An agreed change control process will need to be in place between all parties from the start of any contract, with each potential change assessed for its possible impact on project duration, quality, performance and total costs.
dB Broadcast has developed its own change management process to track and manage all elements of change. The procedure allows control of design changes, so that the impact on other areas of the project, and the overall project programme, can be assessed. It also provides a mechanism for tracking and logging changes.

At the outset of any project, it is essential to have a clear baseline from which change can be measured. A set of documentation would include any or all of the following: a written response to an RFP, a priced Bill of Materials (BoM), stated assumptions, a detailed project plan, project risks, programme approach, resource model, dependencies and key stakeholders. The Project Manager will agree the details of the change process with the client; the change control communication lines and authorities for all parties are defined.

Each proposed change in the client’s requirements will be assessed and submitted for approval before taking action. Projects are typically gated, so that as the design progresses, dB will seek written client approval for changes before instigating them. Changes typically create either a potential delay in project timescales or a cost change, or both. Customers want to be sure they are getting  value for money with changes mid project, as it is impractical to involve competitive tenders at this stage, so dB often agrees commercial terms in advance on how changes are costed. This has a double benefit in that the customer is ensured good value, and dB avoids having to negotiate every change. All major changes will also require a risk assessment, i.e. would the change impact on an existing risk, or create a new risk?

In the high-level design phase of a project, relatively frequent negotiation with the client project team will be expected. Proposed changes are recorded in a change register as soon as they are identified, and may be grouped together into a single contract change for client approval. Urgent client changes mean that a change request will be raised immediately. In the low-level detailed design and installation phases, changes will in general be requested individually, as their impact is likely to be greater than in the early stages of system design. The later in the project the change is requested, the greater its likely impact.

A changes register for the project is used at internal project reviews to assess the impact on the project costs and timescales. The Project Management Office maintains records within each project for all client approvals and tracks the status of each change as 'in progress', 'approved' or 'rejected'.

An effective process for managing change should help minimise surprises when seeking a successful outcome in delivering complex broadcast projects.

www.dbbroadcast.co.uk
VMI.TV Ltd

Top Related Stories
Click here for the latest broadcast news stories.

05/08/2019
Managing Change
Looking ahead and planning for change is essential in most aspects of life. Managing change effectively is an integral part of any project or programm
18/10/2024
World Of Wonder Acquires Its First Scripted Project
World of Wonder has acquired its first scripted project, I Hate People, People Hate Me. Executive Produced by Lauren Corber, Evan Dell'Aquila and Lisa
17/06/2024
Martin Audio WPM Specified For Belgium's Silt Architectural Project
The newly-completed, multifunctional Silt complex—an architecturally sophisticated 'landscaper' completed earlier this year—forms a dominant, wood-lat
04/02/2008
Project Explores Impact Of Digital Cinema
Digital exhibitor kino cinemas, server manufacturer Doremi, software developer SiTec and consultancy peacefulfish have joined forces to launch a pilot
27/03/2018
Interconnection Is Important For Managing Industry Change - Matt George
BFV talks to Matt George, Equinox Senior Manager EMEA UK, about the importance of interconnection and BVE's industry importance. Equinix is the global
18/12/2013
Who's Running Your Next Project?
You have a successful post production facility, and decide to increase revenue by installing another edit suite, grading suite or dubbing theatre. You
28/06/2012
Marquis’ Project Parking Scores For Input Media
Marquis Broadcast, specialist in content workflows and media integration software, has announced Input Media, one of Europe’s leading sports productio
10/12/2013
Input Media Archives With Project Parking
Last year, Marquis Broadcast supplied Input Media, one of Europe's leading sports production companies, with its archive and restore solution, Project
09/06/2014
Marquis: Effective Tools For Efficient Shared Storage Administration
Post Production editors are busy people. In recent years, the number of staff creating content has started to outweigh those who manage it and so some
12/03/2013
The Challenges Of Systems Integration
Whether upgrading or building a new production system, preparation and planning are key to ensuring the project can be completed on budget and on time
28/07/2014
Marquis Broadcast Launches Project Parking V3.8
Marquis Broadcast has announced the launch of Project Parking V3.8. The latest functionality of its edit shared storage management software, Project P
20/03/2024
Limecraft Calls On Industry To Change The Way It Talks About AI
With less than a month to go until NAB Show Las Vegas, mediatech innovator Limecraft is calling on the industry to change the way it talks about Artif
03/05/2019
Share Stories That Change The World With NewTek's Advanced Video Production Solutions
Innovation and technology are the focus of the video industry change agent, NewTek who has always sought to fundamentally change the way video is crea
06/11/2018
MX1 Joins DPP Business Change Network
MX1 has joined the Digital Production Partnership (DPP) business change network and will participate in the DPP Technology Leaders' Briefing 2018, tak
18/08/2017
ASC Technology Committee Announce Name Change
The ASC Technology Committee has been renamed the ASC Motion Imaging Technology Council. Established in 2003, the Committee has helped organize effort